Consistent establishment of safe worksites with a professional team
Our experience enables us to partner with our clients to develop and implement cost-effective traffic management solutions.
Drysdale Bypass
Client
Decmil
Project value
$11m
August 2018 to July 2020
Location
Drysdale, Victoria
Description ALL Set was the traffic management partner for the new $117 million bypass, stretching 6 kilometres from Jetty Road to the north of Whitcombes Road. The new bypass aims to significantly reduce traffic congestion through the centre of Drysdale and ensure safer, more efficient journeys on the Bellarine Peninsula.
Keep Ballarat Moving
Client
Seymour Whyte
Project value
$26m
Date works performed
2022 to 2024 (in progress)
Location
Ballarat, Victoria
Description
ALL Set is supporting the delivery of works that will upgrade the Hertford and Albert Street Intersections.
Barwon Heads Road Upgrade - between Barwarre Road and Marshalltown Road
Client
BMD
Project value
$295m
Date works performed
August 2021 to July 2023
Location
Geelong, Victoria
Barwon Heads Road Upgrade - Barwarre Road to Settlement Road
Client
Decmil
Project value
$295m
Date works performed
August 2021 to July 2023
Location
Geelong, Victoria
Description
ALL Set is supporting the delivery of works that includes: Construction of a new two-lane carriageway. Reconstruction, realignment, rehabilitation and upgrade of the existing carriageway. Upgrade of two signalised intersections and construction of two new signalised intersections. Additionally, we are supporting Decmil to construct a new four-lane bridge over Waurn Ponds Creek, and a cantilever structure for provision of shared use path adjacent to wetlands.
Warrnambool Line Upgrade
Client
Downer
Project value
Total: $510m, Downer section: $114m
Date works performed
Mid 2020 to end 2022
Location
Geelong to Warrnambool
Description
Go Traffic is supporting the $114 million Warrnambool Line upgrade which includes: Construction of a new crossing loop, Signaling upgrades between Waurn Ponds and Warrnambool and Level crossing upgrades.
Princess Highway West - Winchelsea to Colac
Client
Decmil – Warncoort to Colac East
Project value
$363m
Date works performed
2016 to 2020
Location
Colac East
Description
Princess Highway West - Winchelsea to Colac
Client
BMD – Armitage to Warncoort
Project value
$363m
Date works performed
2016 to 2019
Location
South West Victoria
Go Traffic supported works that added extra lanes and built new intersections along the Princes Highway between Winchelsea and Colac to make everyone’s journey quicker and safer. The works stretched out over 35km and included management of daytime traffic volumes in excess of 13,000 cars per day.